Question 1 of 30
A project manager is overseeing a software development project that requires meticulous tracking of time and expenses. The team has logged a total of 320 hours of work over a period of 4 weeks, with an average hourly rate of $50. Additionally, the project incurred direct expenses amounting to $2,000. If the project manager needs to calculate the total cost of the project, including both labor and expenses, what would be the total cost?
$16,000
$14,000
$18,000
$15,000