Question 1 of 30
In a manufacturing company utilizing Microsoft Dynamics 365 for Finance and Operations, the supply chain manager is analyzing the impact of lead time on inventory levels. The company has a safety stock of 200 units, an average daily demand of 50 units, and a lead time of 10 days. If the company decides to increase the lead time by 5 days, what will be the new reorder point, assuming the safety stock remains unchanged?
700 units
600 units
500 units
800 units