Question 1 of 30
A manufacturing company is analyzing its production process to optimize efficiency. They have identified three main operations in their routing: Cutting, Assembly, and Packaging. Each operation has a specific time requirement per unit produced: Cutting takes 2 hours, Assembly takes 3 hours, and Packaging takes 1 hour. If the company plans to produce 100 units, what is the total time required for the entire production process, assuming that all operations are performed sequentially and there are no overlaps in the operations?
600 hours
500 hours
400 hours
300 hours