A manufacturing company is analyzing its production execution process for a new product line. The production manager has identified that the total production time for a batch of products is influenced by both the setup time and the processing time per unit. The setup time for the batch is 120 minutes, and the processing time per unit is 15 minutes. If the batch size is 50 units, what is the total production time for the batch? Additionally, if the company aims to reduce the total production time by 20% in the next quarter, what should be the target total production time for the batch?
1440 minutes
1200 minutes
960 minutes
1800 minutes