Question 1 of 30
A project manager is tasked with overseeing a new mobile application development project. The total budget allocated for the project is $150,000. The project is expected to last for 6 months, with the following monthly expenses projected: $20,000 for development, $5,000 for marketing, and $3,000 for administrative costs. After 3 months, the project manager realizes that the actual expenses have exceeded the budget by 10%. What is the maximum amount the project manager can spend in the remaining 3 months to stay within the total budget?
$85,000
$75,000
$90,000
$80,000