Question 1 of 30
Mr. Adams is a project manager tasked with overseeing a construction project for a new office building. During the risk assessment phase, his team identifies a significant risk of delays due to unpredictable weather conditions in the area during certain months. What should Mr. Adams prioritize as part of his risk treatment plan?
Implementing a contingency plan to manage schedule adjustments.
Ignoring the risk since weather conditions are unpredictable.
Reducing the project scope to minimize potential delays.
Conducting a stakeholder consultation to gather opinions.