Question 1 of 29
A company is evaluating the implementation of a Hyper-Converged Infrastructure (HCI) solution to enhance its data center efficiency. They currently operate a traditional three-tier architecture consisting of separate servers, storage, and networking components. The IT team estimates that transitioning to HCI will reduce their physical hardware footprint by 50%, decrease power consumption by 30%, and improve deployment speed by 40%. If the current infrastructure requires 200 kW of power and occupies 100 square meters, what will be the new power requirement and space utilization after the transition to HCI?
140 kW and 50 square meters
160 kW and 60 square meters
100 kW and 40 square meters
120 kW and 70 square meters