A project, initially estimated to conclude in 12 weeks, encounters an unexpected 3-week delay from a key component supplier. This delay directly impacts Task C, a critical path activity with an original duration of 4 weeks. Assuming Task C is the sole critical path activity affected by this external event, and all other tasks proceed as planned with their original durations and dependencies, what is the revised projected completion time for the entire project?

15 weeks
14 weeks
13 weeks
16 weeks

About the TFINCTAPLIXM2001 ASTFINCTAPLIXM2001FTXA200 Core Technical Certification

These free practice questions are designed to help you assess your readiness for the TFINCTAPLIXM2001 ASTFINCTAPLIXM2001FTXA200 Core Technical exam by Other. Each question comes with a detailed explanation to reinforce the correct concept. For a complete exam preparation experience with hundreds of questions, spaced-repetition study tools, and full exam simulations, explore our premium access.