Question 1
Link to questionDuring Sprint 3, the market for the team\'s digital product experienced a sudden, seismic shift, rendering a significant portion of the planned features obsolete and demanding a rapid pivot towards a new core functionality. The Product Owner has a revised vision and a preliminary backlog reflecting this change, but the Development Team is midway through implementing the original scope. The Scrum Master needs to navigate this disruption while upholding Scrum values and principles. Which action would be most effective for the Scrum Master to take in this situation to ensure the team\'s continued effectiveness and adaptability?
Facilitate a Sprint Review to gather feedback on the revised backlog and guide the team in adjusting the Sprint Goal and plan.
Immediately instruct the Development Team to abandon current work and begin implementing the new features based on the Product Owner's revised backlog.
Organize an unscheduled, informal meeting with key stakeholders to independently re-prioritize the remaining Sprint work based on the new market demands.
Proactively engage with the Development Team to brainstorm and dictate a new technical architecture that aligns with the revised market direction before the next Daily Scrum.
Show answer and explanation
Correct answer
Facilitate a Sprint Review to gather feedback on the revised backlog and guide the team in adjusting the Sprint Goal and plan.
The scenario describes a Scrum Team facing a significant shift in market demands mid-Sprint, requiring a substantial change in the product\'s core functionality. The Scrum Master\'s role is to facilitate adaptation. Option A, \"Facilitate a Sprint Review to gather feedback on the revised backlog and guide the team in adjusting the Sprint Goal and plan,\" directly addresses the Scrum Master\'s responsibilities in managing change and maintaining agility. A Sprint Review is the appropriate event to inspect the Increment and adapt the Product Backlog. By gathering feedback and involving the Development Team in replanning, the Scrum Master ensures the team can pivot effectively. Option B is incorrect because while stakeholder collaboration is vital, unilaterally changing the scope without team and Product Owner consensus during a Sprint Review is counter to Scrum principles. Option C is incorrect because conducting a separate, ad-hoc meeting outside of formal Scrum events might bypass necessary transparency and collective decision-making. Option D is incorrect because while the Scrum Master coaches the team, directly dictating a new technical approach without involving the Development Team in problem-solving undermines their self-organization and expertise. The focus should be on enabling the team to adapt through established Scrum events and principles.