Question 1
Link to questionMr. Roberts, a Product Owner, is in charge of a Scrum team developing a new software feature. During sprint planning, the team estimates the effort required for each user story. One team member suggests inflating the estimates to ensure they meet the sprint goals comfortably. What should Mr. Roberts do?
Accept the inflated estimates to avoid sprint failures.
Discuss with the team the importance of accurate estimates based on historical velocity.
Adjust the estimates downward to challenge the team to work more efficiently.
Delegate the estimation process to the Scrum Master to maintain team morale.
Show answer and explanation
Correct answer
Discuss with the team the importance of accurate estimates based on historical velocity.
In Scrum, accurate estimation is crucial for effective sprint planning and maintaining transparency. Inflating estimates undermines the team\'s ability to improve their velocity over time and violates the Agile principle of simplicity. Discussing with the team about the importance of accurate estimates based on historical velocity encourages collaboration and aligns with Scrum\'s emphasis on empirical process control.