An Agile Release Train (ART) is two iterations into a Program Increment (PI) when a critical external software component, vital for delivering a core PI objective, experiences an unforeseen, significant delay. The expected delivery of this component has now shifted to the end of the next PI. As the Scrum Master for one of the teams most affected by this, what is the most appropriate immediate action to take to support the ART\'s ability to adapt and maintain its trajectory?

Facilitate an urgent ART Sync meeting involving Product Management, System Architect/Engineering, and representatives from affected teams to assess the impact, explore mitigation strategies (e.g., alternative technical approaches, scope adjustments), and collaboratively revise the PI plan and objectives.
Immediately instruct the affected teams to pivot their current work to less dependent features and adjust their sprint goals to focus solely on internal deliverables, deferring any work related to the delayed component.
Escalate the issue directly to the Release Train Engineer (RTE) and demand a formal change request to be submitted to the external vendor, focusing on penalizing them for the delay.
Encourage the teams to work overtime to compensate for the delay, prioritizing the original PI objectives and assuming the external component will eventually arrive as originally planned.

About the SAFe Scrum Master SSM (6.0) SAFe Scrum Master Certification

These free practice questions are designed to help you assess your readiness for the SAFe Scrum Master SSM (6.0) SAFe Scrum Master exam by Scrum. Each question comes with a detailed explanation to reinforce the correct concept. For a complete exam preparation experience with hundreds of questions, spaced-repetition study tools, and full exam simulations, explore our premium access.