Question 1 of 30

A software development team has completed a total of 150 story points over 6 sprints. If they want to estimate how many sprints it will take to complete a new feature that is estimated at 90 story points, what is the estimated number of sprints required?

$\frac{90}{25} = 3.6 \text{ sprints}$
$\frac{90}{20} = 4.5 \text{ sprints}$
$\frac{90}{30} = 3 \text{ sprints}$
$\frac{90}{15} = 6 \text{ sprints}$

About the Oracle Guided Learning Project Management Foundations Associate Certification

These free practice questions are designed to help you assess your readiness for the Oracle Guided Learning Project Management Foundations Associate exam by Oracle. Each question comes with a detailed explanation to reinforce the correct concept. For a complete exam preparation experience with hundreds of questions, spaced-repetition study tools, and full exam simulations, explore our premium access.