Question 1 of 30

A project manager utilizing Microsoft Project 2013 for a complex software development initiative notices a significant resource overallocation for the core development team. This overallocation arises from unexpected delays in the \"System Integration Testing\" phase, which is a direct predecessor to the \"User Acceptance Testing\" phase. The core development team is critical for both phases, and their standard availability is set according to their typical work week, with no specific \"Available to\" dates defined. To ensure that User Acceptance Testing can commence as soon as System Integration Testing is completed, thereby mitigating further schedule slippage, what is the most effective proactive measure to address the resource overallocation within the project\'s scheduling logic?

Extend the "Available to" date for the core development team to the project's final planned completion date.
Manually assign the core development team to specific tasks within the "User Acceptance Testing" phase, overriding the automatic leveling.
Change the dependency type between "System Integration Testing" and "User Acceptance Testing" from Finish-to-Start to Start-to-Start.
Increase the overall capacity of the core development team by 20% to absorb the additional workload.

About the Managing Projects with Microsoft Project 2013 Certification

These free practice questions are designed to help you assess your readiness for the Managing Projects with Microsoft Project 2013 exam by Other. Each question comes with a detailed explanation to reinforce the correct concept. For a complete exam preparation experience with hundreds of questions, spaced-repetition study tools, and full exam simulations, explore our premium access.