A project manager is reviewing the Work Breakdown Structure (WBS) for a complex infrastructure development project, adhering to ISO 21511:2018 guidelines. During this review, it becomes apparent that approximately 35% of the total estimated project effort has not been explicitly decomposed into the lowest-level elements of the current WBS. What is the most appropriate course of action to ensure compliance with WBS principles?

Decompose the remaining 35% of the project scope into the WBS.
Reclassify the unassigned effort as contingency and add it as a separate element.
Delegate the task of decomposing the remaining scope to the team leads without further guidance.
Exclude the unassigned 35% of effort from the WBS, assuming it will be managed through separate informal tracking.

About the ISO 21511:2018 - Work Breakdown Structures (WBS) in Project Management Professional Certification

These free practice questions are designed to help you assess your readiness for the ISO 21511:2018 - Work Breakdown Structures (WBS) in Project Management Professional exam by ISO. Each question comes with a detailed explanation to reinforce the correct concept. For a complete exam preparation experience with hundreds of questions, spaced-repetition study tools, and full exam simulations, explore our premium access.